How to Bid a Painting Job: Production Rates, Paint Math and Lead-Safe Rules

By . Updated November 24, 2026. 21 min read.

Short answer

Measure each surface, turn the quantities into labor hours with production rates you've timed, figure gallons from the data sheet's spread rate, the coats and waste, then add overhead per labor hour and profit as a margin. In this guide's example, a 3-bedroom interior with ceilings, baseboards and 9 doors takes 82 labor hours and $1,264 of materials, and bids at $5,650.

On this page
  1. The walkthrough checklist
  2. Measuring walls, ceilings and trim: formulas and deductions
  3. How to estimate painting labor: production rates and prep time
  4. Materials: coverage, coats, primer and sundries
  5. Pre-1978 homes: the EPA RRP rule and what it adds to your bid
  6. Overhead, markup and margin
  7. A worked painting estimate: a 3-bedroom interior
  8. Three options clients can pick
  9. Interior vs exterior painting bids
  10. What is not included, and change orders
  11. FAQ

How to bid a painting job comes down to three numbers you can check: how much surface you're painting, how many hours your crew takes per unit of it, and how far a gallon really goes. This guide covers measuring (and when not to deduct doors and windows), production rates to replace with your own, coverage math from real manufacturer data sheets, what the EPA lead rule adds on a pre-1978 home, and a fully worked 3-bedroom interior bid with Good, Better and Best options, exclusions and a change order you can copy.

Every number below is either sourced or marked as an example. Swap in your own; the method is what carries over.

The walkthrough checklist

Most of what wrecks a painting job's margin (a color change nobody mentioned, peeling trim, a house built in 1955) was visible at the first visit. Take this list with you:

  • Year built. Before 1978 means the EPA lead rule may apply.
  • Surfaces. Walls, ceilings, baseboards, crown, window trim, doors (one side or both, with frames), closets, railings, cabinets.
  • Colors. Current color, new color, sheen. A big color change or a deep color usually means an extra coat or a tinted primer.
  • Condition. Nail holes, cracks, peeling, water or smoke stains, mildew, glossy trim, old repairs that show.
  • Heights and access. Ceiling height, stairwells, vaulted rooms, ladders or planks needed.
  • Contents and occupancy. Who moves the furniture, wall-mounted TVs, children under 6, pets, working hours, parking.
  • Photos and measurements. Every wall and problem area, and each room's length, width and height.

Write down the client's own words about what bothers them ("the hallway scuffs", "the trim looks yellow"); they become the reasons behind the options you offer. If you'd rather not type it all up at the truck, Itsquoted turns a one or two minute voice memo into a quote with line items, priced from what you said or your team's price book, for you to review before it goes out.

Measuring walls, ceilings and trim: formulas and deductions

For a 12 by 11 foot bedroom with 8-foot ceilings, two doors (entry and closet) and two windows:

Surface Formula Example
Walls, gross Perimeter x height (12 + 11) x 2 = 46 ft, x 8 = 368 sq ft
Doors Count them; a 36 by 80 inch door is 20 sq ft 2 doors = 40 sq ft
Windows Measure each; a 3 by 5 foot window is 15 sq ft 2 windows = 30 sq ft
Walls, net Gross minus doors and windows 368 - 40 - 30 = 298 sq ft
Ceiling Length x width 12 x 11 = 132 sq ft
Baseboards Perimeter minus door openings 46 - (2 x 3) = 40 linear ft

Here's the distinction most estimating advice skips: deduct doors and windows for paint, not for labor. The Painting Contractors Association's measuring standard, PCA P10, says a small opening in a continuous surface "is disregarded and considered part of the continuous surface." It deducts only openings that run floor to ceiling and are wider than five feet, plus any opening of 100 square feet or more, and never cabinets, tubs or showers. That fits how labor works: cutting in around a window takes about as long as rolling the wall it replaced. So use gross wall area for labor hours and net wall area for gallons.

How to estimate painting labor: production rates and prep time

A production rate is how much one painter finishes in an hour, per coat. Labor hours are quantity divided by rate. The rates below are examples for a brush-and-roll repaint of an occupied home with 8-foot ceilings. They show the method; they aren't published industry figures, so replace each one with your own.

Surface Unit Example rate per painter-hour, per coat Your timed rate
Walls, cut in and roll sq ft (gross) 175
Ceilings, flat, roll sq ft 150
Baseboards, brush linear ft 60
Crown molding, brush linear ft 40
Doors, both sides and frame door 0.75 hour each
Window casing and sill window 0.4 hour each

Prep and job time, also examples:

Task Example time
Move furniture to the middle, cover, mask 1.0 hour per room
Patch nail holes and dings, sand, spot prime 0.75 hour per room
Caulk gaps at trim 0.5 hour per room
Scuff-sand doors and frames 0.25 hour per door
Scuff-sand baseboards 150 linear ft per hour
Setup and cleanup 0.75 hour per painter per day
Final walkthrough and touch-ups 2 hours per job

To get your own rates, time three to five jobs by task and divide each quantity by its hours. Measure the same way every time; PCA P10 makes the point that rates from past work are only reliable when the measuring is consistent. Keep separate rates for high ceilings, deep colors and textured walls.

The recoat time on the data sheet decides whether two coats fit in one day: 1 to 2 hours for Benjamin Moore Regal Select eggshell, 4 hours for Sherwin-Williams ProMar 200 HP Zero VOC eg-shel, at 77 degrees F and 50% humidity (sheets linked below).

What a labor hour costs you

Start with the wage. In May 2025, the median wage for painters, construction and maintenance (occupation 47-2141) was $23.75 an hour, with the middle half between $21.46 and $29.65 and the 90th percentile at $37.89, across 225,190 jobs (BLS OEWS; figures pulled from the BLS public data API, because the page blocks automated reading).

Then add what you pay on top of each wage dollar. Say you pay $25 an hour:

  • Social Security and Medicare: 7.65% of wages (IRS Topic 751), so $1.91.
  • Unemployment tax: FUTA is 0.6% of the first $7,000 per employee after the full state credit (IRS Topic 759), and state rates vary. Assume $0.25 an hour for both.
  • Workers' comp: assume $6 per $100 of payroll, or $1.50 an hour. Rates depend on your state, class code and claims, so get your agent's number.

Loaded cost: $25 + $1.91 + $0.25 + $1.50 = $28.66 an hour. As a check, BLS puts legally required benefits (Social Security, Medicare, unemployment insurance and workers' comp) for private-industry construction and extraction workers at $4.22 per hour worked on $32.17 of wages in June 2026, about 13% (ECEC table 4); this example is about 15%. Add paid leave or health insurance if you offer them; the labor rate calculator does the whole build.

Materials: coverage, coats, primer and sundries

How far a gallon goes is printed on the product's technical data sheet. Four examples:

Product and data sheet Spread rate per gallon Wet film Coats, per the sheet
Benjamin Moore Regal Select interior eggshell, N549 (TDS) 400 to 450 sq ft 3.6 to 4.0 mils Two on bare surfaces; one or two on previously painted ones
Sherwin-Williams ProMar 200 HP Zero VOC interior eg-shel, B20-1900 (PDS) 350 to 400 sq ft 4 mils On drywall, one coat of primer and two finish coats
Sherwin-Williams ProMar 200 Zero VOC interior latex primer, B28W12600 (PDS) 400 sq ft 4 mils One coat under two topcoats
Sherwin-Williams Duration exterior satin, K33 (PDS) 250 to 300 sq ft 5.3 to 6.4 mils Two on new, bare surfaces; one for repaint

The spread rate follows from the wet film thickness. A US gallon is 231 cubic inches (NIST); spread one mil (a thousandth of an inch) thick, that's 231,000 square inches, or 1,604 square feet. So spread rate = 1,604 / wet mils. At 4 mils, 1,604 / 4 = 401 square feet, the top of the ProMar range; at 6.4 mils, 1,604 / 6.4 = 251, the bottom of the Duration range. The sheet's number is paint on the wall with nothing lost.

Real jobs lose paint in roller covers and trays, to overspray, and on rough or porous surfaces (Benjamin Moore's rate depends on texture and porosity). So plan this way:

  1. Use the low end of the sheet's range.
  2. Gallons = net area x coats / spread rate.
  3. Add a waste factor. This guide uses 10%; check yours against gallons bought and used on your last ten jobs.
  4. Round up per color, not on the total. Two colors that need 5.2 gallons each are 12 gallons to buy, not 11.

Coats. Two coats is the default on bare surfaces and color changes. One coat can work on a same-color repaint (Benjamin Moore allows one or two on previously painted surfaces), which makes a fair Good option if the quote says so. Sherwin-Williams notes that a drastic color change hides better over primer.

Primer. Spot-prime patches at a minimum, and use a stain-blocking primer over water, smoke and grease stains, as both makers advise. On walls with many patches, consider a full primer coat: the Sherwin-Williams primer sheet warns that spot priming can leave a non-uniform final coat and recommends priming the entire surface. That's a natural Best-tier upgrade.

Sundries. Caulk, spackle, sandpaper, tape, masking, roller covers. Price them as their own line from what your last few jobs used. The painting estimate calculator runs the area, gallon and labor math for you.

Pre-1978 homes: the EPA RRP rule and what it adds to your bid

EPA says about three-quarters of US homes built before 1978 still contain some lead-based paint (EPA RRP program). Its Renovation, Repair and Painting (RRP) rule covers anyone paid for work that disturbs painted surfaces in pre-1978 housing and in child-occupied facilities such as day care centers and preschools, sole proprietors included. Here's how it works as of November 2026.

Does the rule apply to this job?

The trigger is disturbing paint, which usually means prep: scraping, sanding, removing painted trim. The rule doesn't apply when:

  • The home was built in 1978 or later, or it's housing for the elderly or disabled, or a zero-bedroom unit, unless a child under 6 lives there or is expected to (EPA contractors page).
  • The work is minor repair and maintenance: 6 square feet or less of painted surface per room inside, or 20 square feet or less outside. That exception never covers window replacement, demolition of painted surfaces or a prohibited practice, and non-emergency jobs in the same room within 30 days count as one (40 CFR 745.83).
  • The components you'll disturb have been found free of lead-based paint in writing by a certified inspector or risk assessor, or by a certified renovator using an EPA-recognized test kit or a lab test of paint chips (40 CFR 745.82).

Testing isn't required, but EPA's position is that without documentation that the paint isn't lead-based, the rule applies. Scuff-sanding the trim and scraping loose paint in one room can pass 6 square feet quickly, so when in doubt, plan for the rule.

What the rule requires

Requirement What it means on the job Source
Firm certification The company is certified before it does or advertises this work: $300 to EPA, good for five years EPA firm certification
Certified renovator One is assigned to each job; other workers are certified or trained on the job by one. First course 8 hours (2 hands-on), refresher 4 EPA renovator training
Renovate Right pamphlet To the owner (and an adult occupant if the owner lives elsewhere) no more than 60 days before work starts, with a signed acknowledgment (it can be part of your contract) or a certificate of mailing at least 7 days before 40 CFR 745.84, pamphlet
Signs and containment Warning signs. Inside: furniture removed or covered, ducts in the work area closed and covered, floor covered at least 6 feet beyond the work. Outside: ground covered 10 feet out, doors and windows within 20 feet closed 40 CFR 745.85
Prohibited practices No open flame or torching; no power sanding, grinding, planing or blasting without a shroud and HEPA vacuum attachment; heat guns only below 1,100 degrees F 40 CFR 745.85(a)(3)
Cleanup and verification HEPA vacuum, wet wipe, wet mop; then the certified renovator checks sills, floors and counters with EPA's cleaning verification card 40 CFR 745.85(b)
Records Kept 3 years; compliance records to the owner and an adult occupant with the final invoice or within 30 days of finishing, whichever is first 40 CFR 745.86

The pamphlet comes in English and Spanish (Guía para remodelar correctamente). Fifteen states run their own programs instead of EPA, with their own rules and certification: Alabama, Delaware, Georgia, Iowa, Kansas, Massachusetts, Mississippi, North Carolina, Oklahoma, Oregon, Rhode Island, Utah, Vermont, Washington and Wisconsin. HUD-assisted housing must also meet HUD's Lead Safe Housing Rule, and OSHA's lead in construction standard (29 CFR 1926.62) protects your employees, painting included.

This is general information as of November 2026, not legal advice, and rules change: check EPA's or your state's current requirements, or ask a lawyer.

What it adds to the bid: time for containment, cleaning, verification, slower prep and paperwork, plus plastic, tape, coveralls and HEPA vacuum bags. Certification, training and the HEPA vacuum itself go in overhead. The worked bid below prices the same house built in 1965.

Overhead, markup and margin

Overhead is what you pay whether or not a brush moves. Spread it over the labor hours you actually bill. Assumed monthly figures for a four-painter company:

Overhead Per month
Two work vans: payments, fuel, insurance, upkeep $2,200
General liability insurance $450
Ladders, sprayers, drop cloths and equipment wear $350
Marketing $1,500
Software and phones $300
Accounting and bank fees $300
Part-time office help $1,500
Total $6,600

At 600 billed labor hours a month (four painters, after weather, gaps and shop time), overhead is $6,600 / 600 = $11.00 per labor hour. Charge it by the hour, so a long job carries more overhead than a short one.

Profit goes on top, as a margin on the price: price = break-even / (1 - margin). This guide uses a 20% margin, so price = break-even / 0.80. That's a 25% markup on break-even; adding 20% to cost instead gives you only a 16.7% margin. If you run the office yourself, your pay comes out of that profit. The markup and margin calculator converts between the two.

A worked painting estimate: a 3-bedroom interior

Say you run a four-painter company in Columbus, Ohio. A client wants the living room, dining room, hallway and three bedrooms of a 1994 house repainted: walls, ceilings, baseboards and 9 doors, both sides with frames. Ceilings are 8 feet, the windows have drywall returns (no window trim), and the walls get two colors, living areas and bedrooms. You'll send two painters.

Step 1: measure

Room Size (ft) Gross walls (sq ft) Door openings Windows Net walls (sq ft) Ceiling (sq ft)
Living room 16 x 14 480 2 3 395 224
Dining room 12 x 12 384 1 2 334 144
Hallway 20 x 4 384 5 0 284 80
Primary bedroom 14 x 13 432 2 2 362 182
Bedroom 2 12 x 11 368 2 2 298 132
Bedroom 3 11 x 10 336 2 1 281 110
Total 2,384 14 10 1,954 872

Door openings count in each room they open into, at 20 sq ft each; windows at 15. The perimeters add up to 298 feet; minus 14 door openings at 3 feet, that's 256 linear feet of baseboard. Trim area for paint: 128 sq ft of 6-inch baseboard plus 9 doors at about 45 sq ft each (both faces and the frame), so 533 sq ft.

Step 2: labor hours

Task Quantity Example rate Hours
Walls, two coats 2,384 sq ft x 2 = 4,768 175 sq ft per hour 27.2
Ceilings, one coat 872 sq ft 150 sq ft per hour 5.8
Baseboards, two coats 256 ft x 2 = 512 60 ft per hour 8.5
Doors and frames, two coats 9 doors x 2 = 18 0.75 hour each 13.5
Move, cover, mask 6 rooms 1.0 hour per room 6.0
Patch, sand, spot prime 6 rooms 0.75 hour per room 4.5
Caulk trim gaps 6 rooms 0.5 hour per room 3.0
Scuff-sand doors 9 doors 0.25 hour each 2.3
Scuff-sand baseboards 256 ft 150 ft per hour 1.7
Setup and cleanup 5 days x 2 painters 0.75 hour per painter-day 7.5
Final walkthrough and touch-ups 1 job 2 hours 2.0
Total 82.0

That's about five days for two painters.

Step 3: materials

Material Arithmetic Buy Cost (assumed prices)
Premium wall paint, living areas 1,013 sq ft x 2 coats / 400 x 1.10 = 5.6 gal 6 gal
Premium wall paint, bedrooms 941 sq ft x 2 coats / 400 x 1.10 = 5.2 gal 6 gal 12 x $62 = $744
Ceiling paint 872 / 350 x 1.10 = 2.7 gal 3 gal 3 x $40 = $120
Trim enamel 533 x 2 coats / 400 x 1.10 = 2.9 gal 3 gal 3 x $70 = $210
Primer for spot priming 1 gal $30
Sundries Caulk, spackle, sandpaper, tape, masking, roller covers $160
Total $1,264

Wall paint is planned at 400 square feet a gallon, the low end of the Regal Select sheet; the ceiling and enamel rates are assumptions, so use your products' sheets.

Step 4: the price

Line Amount
Labor: 82 hours x $28.66 $2,350
Materials $1,264
Direct cost $3,614
Overhead: 82 hours x $11.00 $902
Break-even $4,516
Price at a 20% margin: $4,516 / 0.80 = $5,645, rounded up $5,650
Profit $1,134 (20.1%)

What the bid works out to per square foot

$5,650 / 1,954 square feet of net wall is $2.89 per square foot of wall, or $5,650 / 872 = $6.48 per square foot of floor in the rooms painted. That includes ceilings, baseboards and 9 doors, so a square-foot price copied from another job misleads. Use it to sanity-check a bid, not to build one.

How much to charge to paint a room

Bedroom 2 alone, walls in two coats and the ceiling in one, as a one-room job:

  • Labor: walls 736 / 175 = 4.2 hours, ceiling 132 / 150 = 0.9 hour, prep 2.25 hours, setup and cleanup 0.75 hour. Total 8.1 hours x $28.66 = $232.
  • Materials: 2 gallons of wall paint (298 x 2 / 400 x 1.10 = 1.6, rounded up) at $124, 1 gallon of ceiling paint at $40, and $40 of sundries: $204.
  • Overhead: 8.1 x $11 = $89.
  • Price: break-even $525, and $525 / 0.80 = $656, so $660.

Inside the whole-house job the same room costs less, because setup and leftover paint are shared: the case for a minimum charge.

The same bid in a 1965 house

With trim prep that disturbs more than 6 square feet a room, a pre-1978 house falls under the RRP rule. Example extra time: containment 0.75 hour per room (4.5 hours), cleaning and verification 1 hour per room (6 hours), slower trim prep with shrouded HEPA-vacuum sanders (2 hours), and pamphlet, signs and records (1 hour): 13.5 hours.

Added line Amount
Labor: 13.5 hours x $28.66 $386.91
Overhead: 13.5 hours x $11.00 $148.50
Lead-safe supplies (assumed) $220.00
Added break-even $755.41
Added price: $755.41 / 0.80 = $944.26 $945

The bid becomes $5,650 + $945 = $6,595, about 17% more. Show the lead-safe work as its own line and put the pamphlet acknowledgment in what the client signs.

A painting estimate template

Interior painting estimate for [client], [address]. Valid until [date].

Scope: Living room, dining room, hallway and three bedrooms: walls (two colors), ceilings, baseboards, and 9 doors with frames, both sides.

Prep: Furniture and floors covered, nail holes patched and spot primed, trim gaps caulked, doors and baseboards scuff-sanded.

Paint: [line and sheen] on walls, two coats; [ceiling paint], one coat; [trim enamel], two coats. Colors chosen by [date].

Price: $5,650. Deposit of [amount] at signing, balance on completion.

Not included: Kitchen, bathrooms, closet interiors, the front door, drywall repair beyond nail holes and small dings, wallpaper removal, heavy items such as pianos or safes. Extra work by signed change order at $50 per painter-hour plus materials.

License and insurance: [license number], [insurer and policy].

For how to word each part, see how to write a contractor estimate.

Three options clients can pick

Keep the rooms the same and vary what clients really choose between: paint line, coats and prep level.

Good Better Best
Walls Contractor line, one coat, same colors Premium line, two coats Premium line, two coats over a full primer coat
Ceilings and trim One coat each Ceilings one coat, trim two Two coats each
Prep Move, cover, patch, spot prime; no caulking Adds caulking Adds sanding all walls and up to 4 hours of drywall repair
After the job A touch-up visit at one year
Labor hours 51 82 118
Materials $676 $1,264 $1,594
Break-even $2,699 $4,516 $6,274
Price $3,400 $5,650 $7,850
Profit per labor hour $13.75 $13.83 $13.36

Each tier is priced from its own hours and gallons with the same rates, overhead and 20% margin; Good plans its contractor-line paint at 350 square feet a gallon, the low end of the ProMar 200 HP sheet. Profit per labor hour is the check: crew hours run out first, so every tier should earn about the same per hour, and here they do.

Describe each step up in one sentence the client can picture: "Better adds a second coat of a premium washable paint and caulks every trim gap." The full method is in Good, Better, Best pricing. In Itsquoted, the three options, optional add-ons and the "Not included" list sit on one quote the client opens on their phone, picks from and e-signs.

Interior vs exterior painting bids

Interior Exterior
Measuring Perimeter x height, plus ceilings Perimeter x wall height, plus gables (base x height / 2), plus soffits and fascia by the linear foot
Spread rate 400 to 450 sq ft a gallon on the Regal Select eggshell sheet 250 to 300 on the Duration satin sheet, at a thicker film
Prep Patch, caulk, scuff-sand Wash, scrape, sand, prime bare wood, caulk; time it as its own line
Weather Benjamin Moore: not below 50 degrees F Duration: air, surface and paint above 35 degrees F and 5 degrees above the dew point, no rain or snow expected within 2 to 3 hours
RRP minor repair limit 6 sq ft per room 20 sq ft
RRP containment Floor covered 6 ft beyond the work, ducts closed and covered Ground covered 10 ft out, doors and windows within 20 ft closed, vertical containment within 10 ft of a property line

Build rain days into the exterior schedule rather than the price, and say on the quote how weather delays move the dates.

What is not included, and change orders

Most painting disputes start with an assumption. Put a "Not included" list on every quote:

  • Rooms and surfaces not listed: closet interiors, exterior doors, cabinets, stair railings
  • Drywall repair beyond nail holes and small dings, or beyond the stated allowance
  • Wood rot, water damage, and anything found behind wallpaper or under failing paint
  • Wallpaper removal and popcorn ceilings
  • Moving heavy items such as pianos and safes; taking down wall-mounted TVs
  • Color changes after the paint is bought or work has started
  • Lead testing, unless it's a line on the quote

Where you can't see how big a repair is, quote an allowance ("up to 4 hours of drywall repair included") and price anything beyond it by change order, at a rate built from your own numbers: ($28.66 labor + $11.00 overhead) / 0.80 = $49.58, so $50 per painter-hour, with materials at cost / 0.80 (25% over cost).

A change order you can copy (hypothetical details):

Change order 1 to the estimate dated [date] for [client], [address]

Change: Repair water-damaged drywall on the hallway ceiling, about 6 sq ft: cut out, patch, tape, three coats of compound, sand, prime, then paint the whole hallway ceiling.

Price: 5 painter-hours x $50 = $250, plus materials $40 x 1.25 = $50. Total: $300. New contract total: $5,950.

Schedule: Adds one day for drying. Finish date moves to [date].

Approved by [client name] on [date]. Work starts after signature.

Get every change signed before the extra work starts, even small ones. If you sign contracts in the client's home, the FTC's Cooling-Off Rule can give the client until midnight of the third business day to cancel many sales of $25 or more made there (FTC); e-signatures on contractor contracts covers that rule and signing on a phone.

FAQ

How do you calculate a painting estimate?

Measure the surfaces, divide each quantity by your production rate to get labor hours, and multiply by your loaded labor cost. Add paint (net area times coats, divided by the spread rate, plus waste), sundries, overhead per labor hour and profit as a margin. In this guide's example, that's 82 hours, $1,264 of materials and $5,650 for a 3-bedroom interior.

What do painters charge per square foot?

It depends on what's included, so use it as a check, not a method. The worked Better bid here comes to $2.89 per square foot of wall, or $6.48 per square foot of floor, including ceilings, baseboards and 9 doors. Good comes to $1.74 per square foot of wall and Best to $4.02.

How much should I charge to paint a room?

Price the room from its own hours and gallons. In this guide's example, a 12 by 11 bedroom with walls in two coats and the ceiling in one takes 8.1 labor hours and $204 of materials, and comes to $660 as a stand-alone job. The same room costs less inside a larger job, because setup and leftover paint are shared.

How many square feet does a gallon of paint cover?

Read it off the product's data sheet: 400 to 450 square feet for Benjamin Moore Regal Select eggshell, 350 to 400 for Sherwin-Williams ProMar 200 HP eg-shel, and 250 to 300 for Duration exterior satin, which goes on thicker. Those rates assume nothing is wasted, so plan at the low end and add a waste factor.

How long does it take to paint a room?

In this guide's example, a 12 by 11 bedroom with walls in two coats and the ceiling in one takes about 8 labor hours including prep and cleanup: one painter, one day. The recoat time on the data sheet (1 to 2 hours for one paint here, 4 hours for another) decides whether both coats fit in that day.

Do I need EPA lead certification to paint houses built before 1978?

Yes, if you're paid for work that disturbs more paint than the minor repair limits (6 square feet per room inside, 20 outside) in pre-1978 housing or a child-occupied facility, unless the components are documented as lead-free. The firm needs RRP certification ($300 from EPA, good for five years) and each job a certified renovator. Fifteen states run their own programs.

What should a painting estimate include?

The scope room by room, the surfaces and coats, the prep, the paint line and sheen, the price and deposit, a "Not included" list, how changes are priced, your license and insurance, and an expiry date. For a pre-1978 home, add the lead-safe work as its own line and the Renovate Right acknowledgment.

About the author

has been a software developer for 25 years and is an AI specialist. He founded Itsquoted, which turns a voice memo into a quote clients can sign on their phone.

Send your next quote before you leave the job

Record a voice memo, review the quote, and send it. Your client picks an option, signs and pays the deposit on their phone. 14 days free.